| Name of power plant |
Location of power plant |
Total output of power plant |
Number and type of equipment of power units (pcs. x type) |
Parameters upstream of turbine plant |
Beginning of commercial operation |
| Boiler |
Turbine |
Pbar |
To C |
Thermo-Electric Plant of ZIL motor works |
Moscow |
160 MW Hot water 660 Gcal/hr Steam 300 t/hr |
3xBKZ-320-170GM 2xPTVM-100 |
1xT-100/110-130-5 |
127.5 |
540 |
1981 |
Thermo-Electric Plant-3 |
Ivanovo |
330 MW Hot water 1584 Gcal/hr |
5xTP-87 2xPTVM-100 2xKVGM-100 |
1xPT-60-130 1xT-110/120 -130 1xPT-80/100-130/13 |
127.5 127.5 127.5 |
540 540 540 |
1991 |
Thermo-Electric Plant-2 Rehabilitation |
Ivanovo |
184 MW Hot water 480 Gcal/hr Steam 508 t/hr |
6xTP-170 2xBKZ-220-160 2xPTVM -100 |
3xPT-25/30-90/10M 1xR-50-130(90)/11 1xPT-60-90/13 |
88.3 127.5 127.5 |
500 540 540 |
1980-1992 |
Novo-Voronezhskaya Nuclear Power Plant. The second circuit of Unit No.5 |
Novo-Voronezh |
(12500) 1000 MW |
Reactor of type VVR-1000 |
2xK-500-65/1500 |
63.8 |
|
1981 |
| Kostroma TPS Update of Monitoring and Control Systems for Units I-VIII |
Kostroma region, Volgorechensk |
3600 8 x 300 1x1200 |
TGMP-114 |
K-300-240 K-1200-240 |
235.5 |
540 |
1989 |
| Dzerzhinsk Heating and Power Plant Modification of the boilers for gas burning |
Gorky region Dzerzhinsk town |
590 MW |
1xTGM-88 2xBKZ-420-140 4x-420-140NGM 4xPTVM-180 |
1xP-50/130-13 1xT-100/130 2xPT-135/165-130/15 |
127.5 127.5 127.5 |
540 540 540 |
|
| Thermoelectric Plant-2. Extension of TEP. Redesign |
Kostroma |
170 MW |
4xBKZ-210-140 4xPTVM-100 |
1xPT-60-130 1xT-110/120-130 |
127.5 |
540 |
1991-1992 |
| Heating and Power Plant No.20 Basic equipment modernization |
Moscow |
690 MW Hot water 2405 Gcal/h |
3xTP-170 3xTP-230 5xTP-87 3xPTV-100 5xPTVM - 100 2xP -180 1xTGM-84B |
4xPT-25-4 1xPT-60-90 4xT-100/130 1xT-100/130 |
88.3 88.3 127.5 127.5 |
500 500 540 540 |
1986-1989 |
| Thermoelectric Plant-2 Extension |
Lipetsk |
515 MW Hot water 1900 Gcal/h |
3xTGM-96B 3xTGME-464 2xPTVM -180 2xKVGM -180 |
1xPT-135/160-130/15 2xPT-80/100-130/13 2xT-110/120-130/13 |
127.5 127.5 127.5 |
540 540 540 |
1978-1991 |
| Cherepetsk TPS Rehabilitation, Units I-IV |
Tula region Suvorov town |
1800 MW 63 Gcal/h |
7xTP-240-1 1xTP-51 2xTPP-100 1xP-50J |
4xK 150/1 3K 300/240-1 |
170.0 240.0 |
550/520 560/565 |
1991-1997 |
| Heating and Power Plant No.1 Rehabilitation |
Ivanovo |
30 MW Steam - 200 t/h Hot water - 200 Gcal/h |
2xGM-50+4xKVG-3GM 2xE-50-3.9-440GM 8xDE-25-1.4-225 GM |
2xR-12/35+1xR-6/35 |
39 |
425 |
2001 |
IvGRES TPS Modification for working as a District Heating Plant |
Ivanovo region Komsomolsk town |
60 Gcal/h |
2xGM50-1,4 |
|
|
|
2000 |
| North-West combined-cycle power plant. Evaporator plant, Condensate polishing plant, I&C of auxiliary plants |
St.Petersburg |
450 MW |
4xKU273/61-8,0/0,65 |
2xT-150-7,7 4xV 94,2 |
77/6 |
522/199 |
2001 |
Mutnovskaya Geothermal PowerPlant. Units 1 & 2 |
Petropavlovsk-Kamchatsky |
2x25 MW |
- |
2xK-25-06Geo |
6.5 |
161 |
2002 |
| Gas-Turbine Power Plant of Central Processing Facilities of Yuzhno-Shapkinsky Oil Field |
Komi Republic, Usinsk City |
4x6 |
|
4xGTU-6RM |
- |
- |
2004 |
| Combined Cycle Power Plant for Rodnikovskaya Generation Company |
Ivanovo region, Rodniki Town |
12 MW |
- |
- |
- |
- |
2008 |
| Tereshkovo GTPP - Combined Heat and Power Plant |
Moscow |
170 MW 150 Gcal/h |
3xHeat Recovery Steam Generators by Aalborg (Denmark) |
1 x Steam Turbine MTD 40CE, Skoda (Czechia) 3xGas Turbine GE LM 6000 PD Sprint (USA) |
4.5 |
463 |
2008 |
| Kojuhovo GTPP - Combined Heat and Power Plant |
Moscow |
170 MW 270 Gcal/h |
3xHeat Recovery Steam Generators by Aalborg (Denmark) 2xPeak-load hot water boilers PTVM-60, Drogobuzhkotlomash (Russia) |
1 x Steam Turbine MTD 40CE, Skoda (Czechia) 3xGas Turbine GE LM 6000 PD Sprint (USA) |
4.5 |
463 |
2008 |
| Yuzhnaya CHP-22 |
St.Petersburg |
450 MW |
Pr-228/47-7,86/0,62-515/230 |
1x Steam Turbine T-125/150-7,4 1x Gas Turbine GTE-160 |
7.26 |
514.1 |
2009 |